Woodstock Site Project

Southwestern Public Health is moving its Oxford County operations to the heart of Woodstock at 712 Peel Street to better serve our clients from one accessible, centrally-located building. The anticipated move-in date is late summer 2027. 

SWPH offices at 1230 Talbot Street in St. Thomas continue to deliver public health programs and services to the community.

Learn more about the Woodstock site project below, including recent updates to the community, phases of renovation and construction, and anticipated service interruptions to be aware of.

Project Phases

Understand the different key phases of this project and anticipated timelines for each stage.

After merging Elgin-St. Thomas Health Unit and Oxford County public health in 2018, limitations were identified of operating public health services from three separate buildings in Woodstock: 410 Buller Street, 93 Graham Street, and a leased dental space at the Oxford County Community Health Centre. Work to explore relocation options was paused in 2020 to prioritize Covid pandemic response.

In 2023, the SWPH Board of Health established the Special Ad Hoc Building Committee to conduct a needs assessment for space requirements, and explore options to deliver public health services more efficiency in Oxford County. The committee reviewed multiple options, including new builds, build-to-lease opportunities, and several properties available to retrofit.

In October 2026, the Board decided to proceed with a plan to renovate approximately half of the available tenant space at 712 Peel Street in Woodstock for public health use, based on location, functionality, and value. This site also better reflects the current space required, which is fewer square footage than the initial needs assessment.

All SWPH sites, including our St. Thomas office, are funded through the annual operating budget that is shared across our obligated municipalities of Elgin County, Oxford County, and the City of St. Thomas, as well as a portion funded by the Ministry of Health.

Timeline: 2020 (paused to prioritize pandemic response); resumed January 2023-October 2026

An open tender was issued to inform a budget associated with renovating 712 Peel Street for public health use. The health unit emphasized a need to align with the Buy Ontario Procurement Directive, and prioritized financial stewardship. The Board of Health evaluated and awarded the tender to Graceview Enterprises in Belmont, Ontario, due to cost efficiencies, timeline, and its commitment to 95% Ontario and Canadian goods and services in alignment with the Buy Ontario Procurement Directive. SWPH is operating within a board approved $5.5 million renovation estimate.

Timeline: Tender awarded by the SWPH Board of Health on October 22, 2026

Renovations are anticipated to begin in November 2026 and continue through summer 2027. Updates will be shared as renovation construction stages are finalized.

Timeline: November 2026 to late summer 2027

Service Interruptions: Anticipated for summer 2027 as the project nears completion. Disruptions will be communicated broadly to inform clients and service providers.

Renovations are scheduled for completion in late summer 2027. 

Timeline: Anticipated for late summer 2027

Service Disruptions: SWPH is committed to limiting service disruptions as best possible during the move. Disruptions can be expected and will be communicated broadly to inform clients and service providers.

Image Below: Artist rendering of the SWPH Lobby at 712 Peel Street, Woodstock.
Credit: architects Tillman Ruth Robinson (aTRR)